Archive Spotting Movements Log & Heads Up

Thread archived by the site administrator
Status
Not open for further replies.
Seems to be there M.O. Back to base ASAP leaving 200+ passengers for each flight stuck at LBA , despite it being open and the runway cleared.
Yes, normal practice however for a time this morning FR24 was showing a single Wizz Air flight from GLA-LBA, so not sure what happened there.
 
Still lots of positioning flights following to disruption of the past two days-
10/2 G-GDFO(Channex 081W) from Birmingham 2210
11/2 G-JZBC(Channex 072W) from East Midlands 0704
11/2 EI-EGA(Ryanair 65) from Liverpool 0740
11/2 G-JZHX(Channex 071W) to Gatwick 0750
11/2 EI-EVR(Ryanair 77) planned from Liverpool 1030
11/2 G-SAJO(Loganair 812P) planned from Newcastle 1725
 
Still lots of positioning flights following to disruption of the past two days-
10/2 G-GDFO(Channex 081W) from Birmingham 2210
11/2 G-JZBC(Channex 072W) from East Midlands 0704
11/2 EI-EGA(Ryanair 65) from Liverpool 0740
11/2 G-JZHX(Channex 071W) to Gatwick 0750
11/2 EI-EVR(Ryanair 77) planned from Liverpool 1030
11/2 G-SAJO(Loganair 812P) planned from Newcastle 1725
So were last nights diversions due to it snowing at LBA?
 
Apparently they were not back before curfew!
You would think, given the extreme circumstances they would have halted the works for a couple of days. Would be surprised given the conditions if any work took place anyway.
 
You would think, given the extreme circumstances they would have halted the works for a couple of days. Would be surprised given the conditions if any work took place anyway.
Couldn't agree more. You would have thought the airport would be trying to help with a tiny bit of flexibility rather than putting up barriers.
 
You would think, given the extreme circumstances they would have halted the works for a couple of days. Would be surprised given the conditions if any work took place anyway.
They have a contractor who is there ready and waiting to do a job, with all the equipment to hand, and that contractor is to complete by a set deadline ahead if the summer schedule. They wouldn't have been able to do anything Thursday night due to the weather, so doing nothing again last night would probably put them behind schedule.

Effectively, when you have a contract, the runway becomes the contractors at a set time. If the airport stops this and the works overrun as a result, the additional work required to complete, can be viewed as out of contract and frankly, will cost a fortune. It's ironically known as 'Dayworks' and is a licence for contractors to print money..In the same way, if the contractor fails to meet the target, then LBA will be compensated under the contract terms. So, LBA telling contractors to just hang on a couple of hours while late aircraft get in, really isn't an option . ATC cover will also be planned around the published hours.

All airlines were notified of the night closure ahead of the winter period and know that if they are late, for whatever reason, they will be flying elsewhere. It's the same at any airport with a single runway.

Regarding the conditions, as long as their were runway slabs accessible to replace, which clearly there were as the runway was in use, then the contractors can work.

Couldn't agree more. You would have thought the airport would be trying to help with a tiny bit of flexibility rather than putting up barriers.
Please see my explanation above.
 
Looks like Wizz have a positioning A321 due in from Katowice at 12:48, maybe related to the tech aircraft?

Should be A321, HA-LXZ as "WZZ405"

Looks like it maybe positioning into operate the extra Bucharest flight WZZ1016 that's due out at 14:00 and was originally planned to be flown by the tech Airbus A321, HA-LXY. But it would seem she remains tech & stranded at LBA so like you say it possibly bringing in some engineers too.
 
Last edited:
Looks like Wizz have a positioning A321 due in from Katowice at 12:48, maybe related to the tech aircraft?
It's late. Two Wizz flights, both from Katowice, (1 x A320 & 1 x A321) are just crossing the North Sea, one behind the other, heading to LBA (1340 hrs).
 
Last edited:
They have a contractor who is there ready and waiting to do a job, with all the equipment to hand, and that contractor is to complete by a set deadline ahead if the summer schedule. They wouldn't have been able to do anything Thursday night due to the weather, so doing nothing again last night would probably put them behind schedule.

Effectively, when you have a contract, the runway becomes the contractors at a set time. If the airport stops this and the works overrun as a result, the additional work required to complete, can be viewed as out of contract and frankly, will cost a fortune. It's ironically known as 'Dayworks' and is a licence for contractors to print money..In the same way, if the contractor fails to meet the target, then LBA will be compensated under the contract terms. So, LBA telling contractors to just hang on a couple of hours while late aircraft get in, really isn't an option . ATC cover will also be planned around the published hours.

All airlines were notified of the night closure ahead of the winter period and know that if they are late, for whatever reason, they will be flying elsewhere. It's the same at any airport with a single runway.

Regarding the conditions, as long as their were runway slabs accessible to replace, which clearly there were as the runway was in use, then the contractors can work.


Please see my explanation above.
For another 5 or 10 minutes???Give over!
 
For another 5 or 10 minutes???Give over!
Sorry but a contract is a contract, and where do you draw the line? What I'm telling you isn't my imagination. I worked as a project manager dealing with these contracts . You might not like it but neither would the contractor when he's waiting to start work and being told to wait.
Anyway, nice of you to be so dismissive!
 
Sorry but a contract is a contract, and where do you draw the line? What I'm telling you isn't my imagination. I worked as a project manager dealing with these contracts . You might not like it but neither would the contractor when he's waiting to start work and being told to wait.
Anyway, nice of you to be so dismissive!
No I do take your point - it's not that I don't like it - none of my business - just seemed very harsh that a loaded aircraft ready to go and likely to be out of the way by curfew or at least a minute or two over could not be afforded that flexibility. Of course a line has to be drawn and I agree 1 or 2 hours is not appropriate - whereas in the circumstances 1 or 2 minutes might be.
 
No I do take your point - it's not that I don't like it - none of my business - just seemed very harsh that a loaded aircraft ready to go and likely to be out of the way by curfew or at least a minute or two over could not be afforded that flexibility. Of course a line has to be drawn and I agree 1 or 2 hours is not appropriate - whereas in the circumstances 1 or 2 minutes might be.
And I agree with you. But I'm sure there are other factors we are unaware of that played a part here.
But I was simply explaining how these contracts within the construction industry tend to work and why it is that the airport may not have the option of delaying handover to the contractor at the specified time, just because there's a flight ready to leave or due in very soon.

On nights where no runway works are happening, such as over the Christmas break, the airport did stay open later than the published hours on a few occasions so the fact they didn't yesterday tends to add weight to my point.
 
Status
Not open for further replies.

Remove Advertisements

Subscribe to help support your favourite forum and in return we'll remove all our advertisements. Your contribution will help to pay for things like site maintenance, domain name renewals and annual server charges.



Forums4aiports
Subscribe

Heads Up!

Flying is the second greatest thrill known to man.... Landing is the first!
i must be a lunatic. Friday 25th Sept will see me doing a daytrip that involves me leaving my flat in Manchester at 1am and not getting back home until after midnight. All because I'm doing a Loch Ness and Scottish Highlands trip.... out of Glasgow
For some weird reason, my days off work tend to involve being out of my flat by 5am and not getting back until 10pm. Back to work and the regular "fix" of 7.40am to 7.15pm hours
Heatwave Mk2 next week?
Some explosive weather build-ups currently in the North of England. What is it like where you are?

Advertisement

Back
Top Bottom
✖
  AdBlock Detected
Sure, ad-blocking software does a great job at blocking ads, but it also blocks some useful and important features of our website. For the best possible site experience please take a moment to disable your AdBlocker.