OAN 85/ 2018 – MAN-TP AIRSIDE CONSTRUCTION PP03
1.0 SUMMARY
1.1 Works are continuing airside to construct new aprons and taxi-lanes and to reconfigure existing airside areas to form the new Terminal 2 Pier 1 and Remote Aprons.
2.0 PROGRAMME
2.1 Overall: Tuesday 21st August until Thursday 1st November 2018.
2.2 Working hours
2.2.1 Day time working within the main site will be Monday to Friday 08:00-06:00L.
2.2.2 Night time working alongside the main site and bordering Taxiway November-Alpha (NA) and Delta (D) will be Sunday to Thursday 22:00-06:00L.
2.2.3 See attached drawing for exact locations of day and night time working.
3.0 SCOPE & LOCATION OF WORKS
3.1 The main works site is at the north-western end of the existing apron, encompassing Taxiway NA, the cul-de-sac sections of Taxiway D and Stands 86, 217, 218, 245 & 247. Stand 85 will become part of these works from 1st October 2018 when it closes permanently. Refer to OAN 83-2018
3.1.1 The main site will be enclosed by a 2-metre high fence and lit with red obstacle lights.
3.1.2 A night-working area alongside the main site and bordering Taxiway NA and D will be set out with lowlevel blocks situated in the grassed taxiway strip.
3.2 The scope of works is: • Excavation of grass areas and laying of new concrete pavement. • Installation of new deep drainage and interceptor tanks.
For full details see:
https://live-webadmin-media.s3.amaz...-2018-man-tp-airside-construction-pp03-fp.pdf