Only had a quick read but it seems to make sense and looks achievable. Satellite pier on the 70s/80s stands, new pier extended south off T2 where the car parks are now along with new stands, taxiway and runway works and extensions to the current buildings. Moving the fuel farm is an interesting move as the previous master plan said how expensive it would be. Works to start soon if the first phase is to be ready for 2031.
Some highlights.
Terminal areas 60% larger.
Stand capacity increasing to 75.
Current share of the Midlands air travel market is 35%, this is expected to increase to 45% by clawing back pax currently using airports in the South east.
Much of the increases are to be within Europe but long haul travel expected to treble in the next 15 years with increased services to the Middle East and South Asia along with reinstated transatlantic services and new routes to the far East.
ATMs to increase from just under 100k to 180k.
Peak departing pax to increase from 3000 p/h to 5500 p/h, arriving pax from 2500 to 3900.
Cargo to increase from 62000 tonnes to 92000 tonnes